Hong Kong authorities have ordered all lift contractors to review the design and construction of landing doors installed over the past 10 years, after a government investigation found missing fire-safety components in lifts in at least 78 private buildings and two public estates.
The director of the Electrical and Mechanical Services Department issued the order in a letter after inspections into lift contractor Taizoom Elevator revealed “serious deficiencies”.
The company is under intense...
Hong Kong orders lift contractors to review doors installed over past 10 years
Global - Asia
Archived
•
October 17, 2026
•
Source: South China Morning Post | https://www.scmp.com/rss/91/feed - Read Original